Stroud District Council will put up to £245,000 into Woodchester Mansion so its staff stay on for a Heritage Fund bid. A bill of up to £3.75m may follow.

Stroud District Council has agreed to give up to £245,000 to the trust that runs Woodchester Mansion. The money keeps its two project staff in post while the trust prepares a bid to the National Lottery Heritage Fund.

Councillors approved the grant at the Strategy and Resources Committee on 8 October. The council announced the decision on 14 October.

The unfinished Victorian Gothic house stands in Woodchester Park, about four miles south-west of Stroud. It is Grade I listed and owned by the district council. The Woodchester Mansion Trust has run it under a 99-year lease since 1989. The National Trust owns the park around it.

Why the money was needed

The trust’s current funding runs out in December. In September 2025 it won a Heritage Fund “resilience” grant of £154,729, with £30,000 of match funding from the council. That paid for a project manager and an events officer, new condition surveys, a governance review and a skills audit.

The officers’ report to the committee says the next Heritage Fund money could not arrive until August 2028 at the earliest. That leaves an 18-month gap. Without cover, it says, “the Project Manager and Events Officer posts will end and progress towards future NLHF applications will stall.”

The trust told the council it could not fund the gap itself. It holds £50,000 in reserves, which its advisers have told it to keep for match funding later.

Bar chart of Woodchester Mansion's funding gap by financial year: £49,000 in 2026/27, £196,000 in 2027/28 and £64,000 in 2028/29, a total of £309,000. The council agreed up to £245,000, covering the first two years
The funding gap set out in the officers' report. The council agreed up to £245,000, covering 2026/27 and 2027/28 only. Source: Stroud District Council, Strategy and Resources Committee, 8 October 2026. Chart by Stroud Today.
Share this chartFacebookWhatsAppX

What the council agreed

The report put three funding options to councillors: £49,000, £245,000 or £309,000. The council’s release confirms it chose the middle one, recommended by officers. The recommended decision was:

  • up to £245,000 from the council’s Council Plan earmarked reserve, for 2026/27 and 2027/28 only
  • a further report back to the committee on 2028/29 funding and on match funding, if the bid succeeds
  • noting that the lease will need to change to meet Heritage Fund rules
  • an option for the National Trust to call for the lease on the mansion once the first phase of work is complete

The council’s release does not mention the National Trust option. The committee’s minutes have not yet been published, so we cannot confirm that part was agreed as written.

The reserve had £737,000 unallocated before this decision, according to the report.

The timetable from here

The report sets out the trust’s planned route to a full bid:

  • December 2026: resilience grant project ends; final report due by 31 December
  • February 2027: Expression of Interest submitted to the Heritage Fund
  • March 2027: decision on the Expression of Interest
  • November 2027: Round 1 application submitted
  • March 2028: Round 1 decision
  • July 2028: development phase begins, with Heritage Fund money from August 2028

The trust chose November 2027 over August 2027 because August falls in the middle of the mansion’s open season.

The bigger bill to come

The £245,000 is not the expensive part. The report puts the likely project at £6.5 million to £7.5 million. If the bid succeeds, the Heritage Fund may expect the council, as owner, to find between 10% and 50% of that. On a £7.5 million project that could be up to £3.75 million. None of that is budgeted, and it would need a separate decision.

Officers also set out what happens if the trust folds. The building would return to the council, and mothballing it would cost “in excess of £50k per annum”. The council already spends about £35,000 a year on insurance and upkeep and gives the trust a £12,000 core grant.

Two other details stand out in the report:

  • the mansion’s chapel is on Historic England’s “Buildings at Risk” register, as the report puts it
  • the trust has separately been awarded £129,000 for work on the North Range, outside this project

Selling the freehold was considered and rejected. The report says it would raise little and “may also face considerable opposition from the local community”.

What the trust and the council said

Cllr Chloe Turner, the council’s leader, said in the release: “Not every council is privileged to own a Grade I listed, unfinished gothic mansion, complete with a rare bat maternity roost, and we’re very mindful of the responsibilities that come with that!”

Rhiannon Wigzell, chair of trustees, said the grant was “a significant step on the way to making sure this unique combination of built and natural heritage lasts for future generations.”

What it means for you

  • The mansion stays open. It is open from 11am to 5pm every Friday, Saturday and Sunday until 1 November, and every day of half term from Friday 23 October to Sunday 1 November, according to the trust’s website.
  • Council tax is not affected now. The grant comes from money already set aside, so the report says there is no impact on the council’s medium-term budget. It does leave less in that reserve for other Council Plan projects.
  • The real decision is in 2027. If the bid goes forward, councillors, or a new Gloucestershire authority if reorganisation resumes, will have to decide whether to find the match funding.

For more days out nearby, see our half-term guide and things to do in Stroud.

Sources