Six years after planning began, volunteers are digging 750 metres of new canal at Eastington, and the River Frome is now diverted under the M5.
Volunteers have started digging a new canal across the fields at Eastington, on a route that was filled in when the M5 was built.
The Cotswold Canals Trust says roughly 750 metres of new canal is being cut east from John Robinson Lock towards the motorway. It is the first construction work ever done on this stretch. The Trust’s own project page puts it plainly: the canal here “was infilled in the early 1970s when the M5 was built so there has been no restoration on this section, until summer of 2026”.
Eastington is about five miles west of Stroud, between Stonehouse and the A38.
The section is called the Missing Mile, and it is the gap that stops the restored Stroudwater Navigation reaching the national waterway network. Stroud District Council says construction began after six years of planning, design and preparation, and after planning permission was granted in June 2024.
What is actually being built
The Missing Mile means reinstating 1.6 kilometres of canal and towpath between the A38 and John Robinson Lock. According to the Trust, the new stretch will include:
- roughly 750 metres of new channel, dug by volunteer teams
- two new locks
- new flood banks either side
- a new towpath
- a mooring basin
- a new canal channel carried through the River Frome beneath the M5
The towpath is being built to a minimum of 2.5 metres wide at the top of the bank, which the Trust says makes it wheelchair friendly.
Progress so far: about 120 metres
The Trust posted a progress update on 6 August. At that point approximately 120 metres of channel had been dug, the bottom levelled, and the banks either side shaped and compacted.
That leaves around 630 metres to go on the eastern side of the motorway.
The build is more exacting than it looks. Because the first stretch crosses a floodplain, the Environment Agency requires the banks to reach a specific height above sea level and to be shaped to an agreed profile, so the floodplain still works in a flood. The Trust describes the method:
- banks built from subsoil, compacted in layers about 300mm thick with a four tonne ride-on roller
- steeper slopes compacted with a remote-controlled sheep’s foot roller
- the canal side of each bank dressed with about 900mm of clay to hold water
- the finished banks topped with topsoil and seeded
Depth, width and bank height are checked constantly with a laser level and a GPS mapping tool.
The M5 crossing
The engineering under the motorway is not a volunteer job. Stroud District Council is acting as Principal Contractor for that element, working with specialist contractors.
The River Frome has already been diverted through an existing culvert beneath the M5, and temporary dams have been installed so the new canal channel can be built in the river bed under the motorway.
Chris Mitford-Slade, the Cotswold Canals Connected project director, said the work “provides a blue-green corridor under the M5 for the first time since 1969, reconnecting communities and bringing benefits to a wide range of people”.
David Hagg, chair of trustees at the Cotswold Canals Trust, called the start of construction “a truly historic moment” and said it reflected “the extraordinary commitment of our volunteers, partners and supporters”.
Where the money came from
The Missing Mile sits inside Cotswold Canals Connected, a partnership led by Stroud District Council and the Cotswold Canals Trust with the Canal & River Trust, Gloucestershire County Council, the Stroud Valleys Canal Company and Gloucestershire Wildlife Trust.
- The programme has had £15.4 million from The National Lottery Heritage Fund.
- In November 2025 it was awarded a further £6.46 million specifically to deliver Phase 1B, after Covid delays and construction inflation blew a hole in the original 2020 funding.
- The A38 roundabout crossing, completed in 2020, was built by county council contractors with a £4 million grant from National Highways’ Environmental Designated Funds scheme.
Phase 1B is the whole 6 kilometre stretch, about 3.7 miles, from Saul Junction on the Gloucester & Sharpness Canal to the Ocean Railway Bridge at Stonehouse.
What it means for you
- If you walk the towpath at Eastington, the footpath alongside the south bank of the River Frome is temporarily closed. A signed diversion runs through the Missing Mile site, so walkers can still get through.
- If you drive the M5 near Junction 13, the work under the motorway is happening in the river bed, not on the carriageway. No M5 closures are attached to it. Live closures are on our Stroud roadworks and travel page.
- If you want to help, the dig is volunteer-led and the Trust says volunteer working days have been increased to keep the excavation on schedule.
- If you are waiting for boats, this is not that moment. The Trust aims to reopen the Stonehouse to Saul Junction stretch to navigation by 2029.
Who came to see it
The Trust held an open and press day at the site in the week to 20 August. Those who attended included Dr Simon Opher MP, the MP for Stroud, and Stuart McLeod, director of England, London and South at The National Lottery Heritage Fund.
McLeod said the project was “restoring a vital corridor for nature after the landscape was divided by the M5”.
The Trust says construction will carry on over the coming months, with regular updates as it goes.
Sources
- Construction Begins on the Missing Mile, Stroud District Council, 21 August 2026, issued by the Cotswold Canals Trust on behalf of the Cotswold Canals Connected partnership, for the start of construction, the June 2024 planning permission, the River Frome diversion, the footpath closure, the £15.4 million and the quotes.
- Missing Mile Update: 120 Metres Complete and Counting, Cotswold Canals Trust, 6 August 2026, for the metres dug, the Environment Agency bank requirements, the 2.5 metre towpath width and the construction method.
- Phase 1B, Cotswold Canals Trust for the 6km route, the 1.6km Missing Mile between the A38 and John Robinson Lock, the early 1970s infilling, the November 2025 award of £6.46 million and the £4 million National Highways grant for the A38 crossing.
- A Milestone for the Missing Mile: Supporters Gather to See Restoration Progress, Cotswold Canals Trust, 20 August 2026, for the open day and who attended.
- Stroud District Council update, w/c 24 August 2026 for the council’s own summary of progress.
All sources checked on 30 August 2026. What is being built elsewhere in the district is on Stroud planning news, and live road closures are on Stroud roadworks and travel.